130 Liberty Street Deconstruction Plan Documents
The Deutsche Bank Building at 130 Liberty Street
Below is a list of the Draft and Final Approved Deconstruction Plans for 130
Liberty Street.
5.14.09 & 5.15.09 Agency Acceptance Letters for Implementation Plan and EHASP
Final Implementation Plan for Deconstruction and Decontamination and Environment, Health, and Safety Plan and Emergency Action Plan
- 130 Liberty Street Contractor's Implementation Plan for Decontamination and Deconstruction
- 130 Liberty Street Contractor's Implementation Plan for Decontamination and Deconstruction (REDLINE VERSION)
- May 21, 2009 130 Liberty Implementation Plan Amendment 1
- November 13, 2009 130 Liberty Implementation Plan Amendment 2
- December 9, 2009 130 Liberty Implementation Plan Amendment 3
- Environment, Health & Safety Plan and Emergency Action Plan for the 130 Liberty Street Building Abatement & Deconstruction Project
- Environment, Health & Safety Plan and Emergency Action Plan for the 130 Liberty Street Building Abatement & Deconstruction Project (REDLINE VERSION)
- November 11, 2009 130 Liberty EHSP Amendment 1
Transcript for 130 Liberty Street Public Meeting on March 5, 2009
Public Comments for Deconstruction Plan Documents
Response to Public Comments
Draft Documents:
- 130 Liberty Street Contractor's Implementation Plan for Decontamination and Deconstruction
- Environment, Health & Safety Plan and Emergency Action Plan for the 130 Liberty Street Building Abatement & Deconstruction Project
Noise Mitigation Program Notarized March 27, 2009
Approved February 2008 Addendum to September 7, 2005 Deconstruction Plan
September 7, 2005 Final Approved Deconstruction Plan
NYC Department of Buildings Information
Monthly Progress Reports
130 Liberty Street Deconstruction Plan Archived Documents